Mawacon informs: Updated construction schedule for fiber optic expansion


At the end of 2023, Mawacon began rolling out fiber optics to the municipalities in the VG Winnweiler on its own account. Self-economically means that Mawacon has not been commissioned by the local municipalities, the association municipality or the district and that no public funds are being used for the expansion.

Mawacon had presented a construction schedule at the end of 2023, which had also been published accordingly. There have since been changes here. For example, the work in Imsbach, Lohnsfeld, Potzbach and Sippersfeld has been brought forward. In other places, there have been delays. This is mainly due to construction processes and necessary approvals, such as highway, railroad and water crossings. Approvals from higher-level authorities are required for these, which sometimes take longer to process.

Mawacon has now provided the local authority with an updated construction schedule, which we would like to share with you below:

Updated Mawacon construction schedule

Municipality

Start civil engineering

End of civil engineering

Start of technical commissioning

Completion of technical commissioning

Börrstadt

11/2025

22/2025

18/2025

23/2025

Breunigweiler

08/2025

19/2025

16/2025

21/2025

Falkenstein

18/2025

29/2025

26/2025

31/2025

Gonbach

40/2024

50/2024

47/2024

01/2025

Höringen

08/2025

19/2025

16/2025

22/2025

Imsbach

28/2024

50/2024

48/2024

03/2025

Münchweiler/Als.

34/2024

43/2024

40/2024

45/2024

Schweisweiler

08/2025

19/2025

16/2025

21/2025

Sippersfeld

36/2024

47/2024

44/2025

49/2025

Wartenberg-Rohrbach

04/2025

16/2025

14/2025

21/2025

Winnweiler

01/2024

52/2024

38/2024

04/2025

OT Hochstein

05/2025

16/2025

14/2025

19/2025

OT Alsenbrück-Langmeil

05/2025

14/2025

12/2025

17/2025

If you have any questions, please contact Mawacon at the Servivepoint in Kirchstraße (formerly Optik Krupp) in Winnweiler or at www.mawacon.eu.